Importing Chart of Accounts or Suppliers
If you would like your chart of accounts or suppliers uploaded into your
PO book you will need to download the import file, to do this go to Admin >
Import.
Once you have been provided with the import document you will need to
send this over to support@sargent-disc.com with the project name
you would like this imported into.
*Note, this request must come from the Project Admin.
Sargent-Disc will then upload the chart of accounts / suppliers into
the requested project.
If at any point you would like to add additional account codes/
additional suppliers into the system i.e. an extra 5 suppliers then the admin
of the DPO project can do this by going to Admin > Supplier / Admin >
Chart of Accounts.
Related Articles
Creating PO's with existing suppliers only
PO's can be created with existing suppliers only that have been setup under the Suppliers section in administration. If you would like to have this option enabled so users cannot add new suppliers into the system and only create PO's with existing ...
PSL/GV export file showing the Account Description and not the Account Code
If the XML file is showing the account description instead of the account code then the file will fail during import. When using the export function to import into Global Vista or PSL the 'show in export' must be set to Account Code. To change this, ...
Account Name/ Account Code not showing on PDF
If the Account Name or Account Number is not showing on the PO PDF then have the administrator of the DPO project do the following: Go to Administration > Chart of Accounts > On the drop-down menu for 'Show in PDF' there will be 3 options: Show ...
Coding PO's into DPO to upload into Global Vista
If your chart of accounts layout in Global Vista is e.g.: LO G/L DETL ST IN F F2 And you wanted to code this against a PO in DPO as e.g.: LO= 01 G/L=150 DETL=1100 ST= IN= F=A F2=10 You would need to enter this into DPO as: 011501100 A10 The ...
Supplier List Export from DPO
Export your data and open it in Excel as usual, to export the data the admin will need to go to Admin > Export and download the .csv file. Delete all of Columns A to Y (Project ID to Creator Position) After that delete from Column O onwards ...